Latest Information
The overall scheme design continues to develop. Design of the canal overflow is complete, and the planning application submitted. Detailed design for fluvial scheme (Hebden Water and River Calder) is in the final stages and nearing completion. The surface water scheme design continues to progress. The planning application for the fluvial and surface water scheme is forecast to be submitted in early 2024. A public information event will be held ahead of planning submissions to provide more information about the scheme proposals.
Written updates for the Hebden Bridge Flood Alleviation Schemes Key Stakeholder Group can be viewed here:
See links below for the latest information about the scheme:
Keeping You Informed - Resurfacing Work - November 2023
Please note that due to weather conditions the resurfacing work was unable to be carried out on Tuesday 14th November. The work will now take place on Tuesday 21st November.
Click here to view our Google Map of work in the area
Keeping You Informed - Old Gate Closure - November 2023
Keeping You Informed - Ecological Surveys
Keeping You Informed - Vegetation Management Work - September 2023
Keeping You Informed - Trial Hole Work - August 2023
Current forecast project timescales can be viewed here
Past 'Keeping You Informed' notices can be viewed below:
Keeping You Informed - Information Centre Open - August 2023
Keeping You Informed - GPR Surveys - August 2023
Keeping You Informed - Trial Holes - May 2023
Notice - Bridge Gate Investigation Work - February 2023
Keeping You Informed - Vegetation Management and Town Hall Drop-in Dates - October 2022
Keeping You Informed - Town Hall Drop-in Dates - August 2022
Keeping You Informed - Canal Overflow Planning Application - July 2022
Keeping You Informed - Ground Investigation Work - August 2021
Keeping You Informed - Canal Overflow - Planning Submission - August 2021
Keeping You Informed - St Pol Square Car Park Temporary Closure - June 2021
Keeping You Informed - Flood Siren Test - April 2021
Keeping You Informed - Vale Centre Remedial Work - February 2021